Takt time formulation are as follow:
T = Ta / Td
T = Takt time (Net time available for production in Minutes/ unit produced per customer demand)
Ta = Net time available ( minutes of work per day - this exclude rest/lunch/meetings etc)
Td = Time demand (customer demand) e.g. (units required/day)
For example:, if you work 8 hrs a day for 5 days a week. For a week, you have a demand of 100pcs, Then the Takt time calculation should be as follows:
Takt = 8 x 5 x 60 minutes/ 100 pcs
= 24 minutes
By sticking to Takt time, we will have few advantage as follows:
- no over production
- no rush on order
- production planning easily done without interruption
- system work based on customer demand
- reduce or eliminate WIP